Swimming Pool at Park Hotel “Golden Beach”
Year of construction: 2023–2024
Total Pool Area: 1800 m²
Facing of the pool bowl - liner, facing of the side - side stone
Commissioned in 2024
The following work was performed:
- Installation of embedded elements and piping
- facing of the bowl with a liner and the side with side stone
- Installation of filtration equipment
- Pool heating system installation
The pool has:
- Sand filtration
- Automatic water top-up system
- Chemical dosing and control station
- LED lighting
- Control panel and equipment protection