PRIVATE POOL IN DNIPRO
Concrete pool
Year of construction - 2021-2022
Size 8,00 × 4,00 × 1,20 - 1,55 m
Facing of the pool bowl - PVC liner
Commissioned in 2022.
The following work was performed:
- development of an individual pool project
- making pool bowl
- installation of embedded elements of filtration system and piping
- installation of liner
- lining the pool edge with coping stone
- installation of technological equipment of the pool.
- commissioning
The pool has:
- color LED lighting
- filtration system
- water heating (heat exchangers)
- automatic control and dosing station Cl and pH
- equipment control and protection unit IP65